New refrigeration unit in workshop N-13-14A new refrigeration unit was put into operation at JSC “SPP” in workshop N-13-14, where technical and crystalline agidol, agidol 0, agidol 2 and agidol 30 are produced. The project was developed a few years ago, and start up and commissioning began in August 2020, and in the summer of this year, after the delivery of all the necessary documentation and receiving a positive opinion from the inspector of Rosgortechnadzor, the installation began to function. The main function of the new unit is additional cooling of the coolant from the AKHU-1 to the specified temperatures based on the installation regulations for the needs of the consumer workshops. It became necessary to increase the capacity and reset the load from the existing installation (AKHU-1) and increase productivity. At present time the installation is operating normally under the round-the-clock control of shift personnel. |
|